Monday, March 30, 2020

Turkey Creek Ph 1 - RL Persons (L.S.)


7:00am- concrete crew only onsite to place rebar and hatches for lid. Possible pour on lid this afternoon.

12:40pm- Hatches are placed and bottom rebar is getting tied. 





3:20pm- top layer of rebar is tied, but a couple of issues. Rebar needs placed under corner of lids. 

Now fixed. 

4:10pm- concrete getting placed. Testing was done with the following results; Air: 4.5%, Slump: 4”, Temp: 62*F. 3 cylinders are made. 

5:45pm- final touches going on top. 



I’ll be headed offsite now. 