7:00am- concrete crew only onsite to place rebar and hatches for lid. Possible pour on lid this afternoon.
12:40pm- Hatches are placed and bottom rebar is getting tied.
3:20pm- top layer of rebar is tied, but a couple of issues. Rebar needs placed under corner of lids.
Now fixed.
4:10pm- concrete getting placed. Testing was done with the following results; Air: 4.5%, Slump: 4”, Temp: 62*F. 3 cylinders are made.
5:45pm- final touches going on top.
I’ll be headed offsite now.