6:30am- Crews onsite to continue with removal of forms and laying ductile pipe.
7:00am- grouting around floor and walls on Liftstaion to take place this AM.
11:30am- grouting at walls and floor in Liftstaion now completed. Also floor in valve vault is sloped to the drain.
Fittings also going together for valve vault at this time.
1.30pm- crew begins set valves and such in the valve vault this afternoon.
5:30pm- plumbing in valve vault almost complete!