Wednesday, March 25, 2020

Turkey Creek Ph 1 - RL Persons (L.S.)


6:30am- Crews onsite to continue with removal of forms and laying ductile pipe. 

7:00am- grouting around floor and walls on Liftstaion to take place this AM. 

11:30am- grouting at walls and floor in Liftstaion now completed. Also floor in valve vault is sloped to the drain. 



Fittings also going together for valve vault at this time. 

1.30pm- crew begins set valves and such in the valve vault this afternoon. 

5:30pm- plumbing in valve vault almost complete!



  