Crew to be onsite today to attempt to lay more pipe. Iowa Trenchless will not be back until around the 7th of April. More blasting is needed in the bore pit on Laytons, but water is an issue there now.
12:00pm- 4th joint of pipe going in now as crew has laid up to the encasement crossing at STA 85+65. Rebar cage is getting installed as they go. Pipe is laid on blocks for grade purposes and to allow concrete under the pipe.
1:15pm- water is pouring into ditch as the crew will have to break rock with hammer due to a high spot.
4:30pm- 6 joints of pipe now laid. Cage is in place and concrete begins going in.
5:55pm- concrete still going in on encasement.
7:35pm- encasement now completed. Crew will call it a day.