7:12am- Pipe is getting moved this morning as crew will be digging from MH A21 laying pipe.
8:10am- laser is now set up and aligned with MH A22 location.
9:10am- 1st joint in for today, but rock is encountered where the blasting never broke it.
10-40am- 2nd joint of the day + a 5.5’ piece that was a cut off from last Fridays tie in at MH A21. So 33.5’ so far today. Starps also being installed on manholes.
1:00pm- 47.5’ now placed.
2:00pm- Survey was out today and shot the top of pipe at 61.5’ upstream from MH A21. This shot was 1.6” low from plan grade which is inline due to them starting 1.5” low at MH A20 to begin with.
3:30pm- 75.5’ now laid in place and more rock is encountered that needs broke by hammer.
4:14pm- 89.5’ of 27” sdr35 now laid in place for the day. Crew will begin backfilling the trench now.
I am headed to Liftstaion site.