Friday, March 13, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Flat Creek will lay pipe again today and Iowa Trenchless will finish up casing today. I calculated footage wrong yesterday; instead of 126’ @9 joints, it should have been 112’ @ 8 joints. 

8:45am- rock breaking occurs on the first joint for today. 

9:10am- 1st joint today getting gravel. 

9:55am- 2nd joint. 

10:50am- 3rd pipe now laid. 

12:50pm- 4th pipe going in. 

2:00pm- joint 5 is in now as grading for joint 6 is underway. 

2:15pm- 6th joint now placed. 

3:15pm- 7th pipe now in place. 

4:05pm- crew has laid their 8th and final joint for today. 112’ of 27” sdr35 laid today. 

4:20pm- backfill begins. 