7:00am- Flat Creek will lay pipe again today and Iowa Trenchless will finish up casing today. I calculated footage wrong yesterday; instead of 126’ @9 joints, it should have been 112’ @ 8 joints.
8:45am- rock breaking occurs on the first joint for today.
9:10am- 1st joint today getting gravel.
9:55am- 2nd joint.
10:50am- 3rd pipe now laid.
12:50pm- 4th pipe going in.
2:00pm- joint 5 is in now as grading for joint 6 is underway.
2:15pm- 6th joint now placed.
3:15pm- 7th pipe now in place.
4:05pm- crew has laid their 8th and final joint for today. 112’ of 27” sdr35 laid today.
4:20pm- backfill begins.