Wednesday, March 4, 2020

Turkey Creek Ph-1 Flat Creek (Line Work)


7:15am- met with Bill from Rail Pros along with Iowa Trenchless and Flat Creek. 

7:40am- J-Mark surveying is also onsite to take shots on the rails. 

8:17am- cutters touch concrete!



Wooden wedges are driven along casing to keep it centered. 

9:01am- material begins exiting the augers. 

9:40am- 2nd joint of pipe is laid so far today. 

11:40am- 4th joint of pipe now laid in place. 

1:35pm-5th joint now laid and Boring crew is nearing 10’ so far. 



3:05 pm- more rock had to be broke...still at 5 joints. 

3:45pm- 6th joint now in place. 

4:55pm- approximately 18’ of casing is now in the ground at bore pit RR04. 



Crew pulls power unit from hole for tonight. 

5:25pm- due to hitting rock all day the crew laid 6 joints of pipe today or 84’ of 27” sdr35. 