7:35am- crew has changed some today and for the future. Two guys have been moved offsite and we now have a new pipe layer. Water is being pumped first thing.
9:10am- 1st joint for today going in.
9:35am- bedding on 1st joint.
10:10am- 2nd joint goes in. Bedding getting placed.
11:30am- 5th joint now in and bedding is getting placed.
1:30pm- 6th joint now in place for today.
2:50pm- the crew allowed water to back up in ditch when pump was getting moved and the 6th joint has floated up by several inches. Crew is now in the process of pulling the joint and relaying it. I am now headed to WWTF for pouring of the top on Liftstaion.
5:00pm- Im back now and they say the pipe was fixed and the 7th joint for today was laid. Crew will fix roadway and cleanup some to finish out their day.