6:40am- Rebar to be tied for floor of vault today and P-Trap set and stubbed through the wall. Possible pour this afternoon. No crew onsite at this time.
10:15am- rebar is in and water stop going in. Pour will occur later this afternoon.
11:00am- just heard from Brian and they can get concrete at 12:00. I will be present to test.
12:05pm- Finishing touches happening before concrete arrives.
12:10pm- concrete arrives and the following results of the test are as follows; Air 6%, Slump 4.5”, Temp 65*F. Four cylinders were made. Pour is going well.
1:00pm- finish work is underway.
5:40pm- rebar mats going up on liftstation walls.
Crew will be placing rebar the rest of this week.