Wednesday, March 11, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:15am- Raining with one crew member onsite at this time. 
8:00am- Iowa Trenchless will be onsite shortly to begin again today. Delay due to the rains and lightning. 

8:50am- Flat Creek crew now digging to lat pipe today. Jimmy is back. 

9:55am- 1st joint of the day is laid. 

11:05am- 2nd joint now laid in place. 

12:05pm- 3rd joint going in. 
1:25pm- 4th joint in place. 

2:55pm- 5th joint now in place. 

3:40pm- 6th joint now in. 

Straps on manhole A22 also inplace. 

4:25pm- 7th joint for today ...

5:15pm- 8th joint now laid. 

6:00pm- 9th and final joint for today. 126’ of 27” sdr35 laid today. 

6:40pm- Due to the time and having to wait on Access Road 3 to be graded so I can get out, I will not visit the Boring site tonight. I will update that site in the morning. 