Crews will try and work between showers today. 
9:35am- crews are onsite now as more forms are getting taken off Liftstaion. Other crew will continue with getting ductile pipe tied into meter pit today. 

Drain line will be opened up to allow water to drain out. 

10:05am- Down pipe is installed in lift station now as crew is tightening the bolts. Temporary wood braces are used under the end of the pipe until pipe supports are installed. 

11:00am- ductile now enters meter vault. 

11:45am- flow meter now getting bolted up. 

1:40pm- spool and valve now in place. 

3:05pm- lid now going on meter vault. There is no safety grate in this lid and RL Persons is aware of it and have made a call to the supplier at this time. 



4:40pm- check valves and supplies are gathered as crew goes through them to ensure all parts are onsite for placement in valve vault later this week. 

5:00pm- I’m now headed offsite. 