Tuesday, March 10, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:40am- Boring contractor is now in about 70’. They virtually flat at this point with grade. They cannot get their head to cut any deeper. Power unit going back in hole to begin cutting. 

8:10am- 1st joint of pipe laid today.

8:50am- 2nd joint going in. 

- progress meeting today. Discussion of how pipe is getting laid with out Jimmy being here right now. 
I asked that the rubbers be throughly checked due to water continuously running across them with silt and such. Kenny and Chris stated that Jack needed supervision. 
12:55pm- MH A22 base going in right now. 42’ of 27” sdr35 is laid to manhole A 22 today. 

1:35pm- barrel section on and upper section  now going on MH A22. 

2:25pm- Line from MH A22 to MH A21 is lamped. 

3:55pm- 1st joint now upstream of MH A22 is laid. 

4:55pm- 2nd joint upstream of MH A22 now placed. A total of 5 joints or 70’ of 27” sdr35 laid today and MH A22 set. 
Backfilling will round out the day now. 

5:40pm- Boring contractor has 80’ now in and are working on the 5th 20’ section.  

5:45pm- I'm headed offsite. 