Monday, March 23, 2020

Turkey Creek Ph 1 - RL Persons (L.S.)


6:40am- more forms to come off today and the other crew is back to  work on more ductile. 

9:00am- gravel going down for meter pit. Compaction taking place and blocks set for vault to sit on so that floor can be poured later today. 





12:30pm- box is checked for square to valve vault. Concrete is ordered for pouring floor here shortly. 

2:00pm- concrete floor going in for meter vault. 





2:40pm-Floor now complete. 

3:55pm- more ductile is bolted together for down pipe in lift station. 

5:00pm- forms still coming out of station. 