8:00am- rock is getting hauled to roadway while pumps are pumping to get water from ditch.
Excavator has to smooth up roadway so I can get in.
8:30am- ditch has a bunch of water still running through it.
9:45am- excavator backfilling over concrete encasement in between loading haul truck with rock.
10:40am- ditch is now opened on up for pipe to begin getting laid today.
11:45am- crew digging a bench so pump can be lower.
12:50pm- ? Pumps are getting moved now???
1:25pm- pump is set back up at pipe end of ditch and is getting primed.
2:15pm- water is now below pipe, but laser is moving all about...crew is deciding what to do about it.
3:40pm- crew is calling it a day due to the uncertainty of the laser. Water is now filling hole back up.
5:00pm- area of 12” line where project started near Sub Station is getting graded out and soul applied to it.