Tuesday, January 28, 2020

Turkey Creek Ph 1- Flat Creek (line work)


8:06am- Starting to excavate heading South out of MH-35 towards MH-36



8:20am- Setting first stick of 12” SDR 35 pipe for the day
8:51am- Continue to excavate South out of MH-35

9:10am- Setting several more sticks of SDR35 pipe



10:48am- Moving towards MH-36 and setting SDR 35 pipe. 112’ so far this morning.