Wednesday, January 15, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:45am- Blasting crew onsite to shoot the wall of rock. 

It shot ok, but broke the slope anchor back board with dirt that flew. 



Crew pulls section of broken pipe and will begin to re-dig. 

8:30am- Skidsteer has lost a track so crew will be working to it it back on. 

9:10am- crew is now back to digging to re install a new joint of pipe. 

1:25pm- crew has now laid 7 joints of pipe today. A discussion of making sure there is 12” clean gravel over the pipe leveled across the entire width of the ditch took place again today. Crew has stated that they know this and more gravel will be applied before backfill. 

5:20pm- 5 slope anchors are almost built. Crew will finish with rest of the rebar install in the morning. 