Crew is back to digging this morning and will be to MH A 35 to set it here shortly.
8:50am- 4th joint for the say going in.
10:25am- Digging at MH A35 now.
Loads of blasted rock getting hauled offsite today also.
12:15pm- MH A35 base is now set with 119.58’ of 12” sdr35 laid to manhole. Line is also lamped back to MH A34.
1:30pm- Lase is now rest in MH A35 and lined up on next manhole location. Digging back underway.
2:35pm- roughly 20.5’ is now laid upstream of MH A35. I have at this time let Chris with Flat Creek know that there is getting to be a-lot of finer material in the bedding. He stated he would call the quarry.
4:00pm- crew has now laid 76.5’ of 12” sdr35 upstream of MH A35 bringing todays grand total of pipe laid to 196.18’.
Digging will now cease and crew will move to finish stacking out previous manholes.
5:15pm- crew is packing things up to call it a day. Previous manholes are now stacked on out from A31- A34.