Manholes are due to arrive for the 12” line this AM. Crew will unload them at substation area.
7:45am- Laytons roadway washed just a little from all the rains. Ditch is plugged.
9:35am- Crew is awaiting arrival of a trackhoe so that they can unload manholes that have been onsite since 7am.
Also at this time the Dozer is moving material on down the hill at substation getting it ready to dig.
11:45am- Manholes have now been unloaded and are getting moved to their respective locations.
1:45pm- Crew just starts digging at MH A30 and another load of manholes shows up.
3:30pm- MH A30 base is now set in place.
5:20pm- crew has now dug out for a joint of pipe. Gravel will be placed tomorrow so pipe can begin to be laid.