Thursday, January 2, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:30am- Crew starting brush pile on fire this AM. Clearing on to the tracks will occur and the moving of equipment to Laytons property to take place later today. 

9:55am- Just a couple more big trees and this end will be good to go. 



11:00am- Drilling now occurring around STA 122+00. A blast will also happen today after lunch. 

1:50pm- Dozer is now on Layton beginning clearing. 

2:45pm- Blasting crew loading holes. Should blast within the next 45 minutes. 

3:25pm- Blast goes off with out any issues. 

4:50pm- Clearing on Layton is going good. 





5:00pm- Brush piles are still burning; I have asked that someone keeps an eye on them to ensure no out of control burn takes place. 





5:20pm- I am now headed offsite. 