8:00am- Crew finishing installation of rebar for slope anchors. Concrete to be poured today.
8:53am- More gravel going in over pipe now.
9:35am- Concrete going in now.
9:50am- top one done.
10:00am- next one down nearing completion.
10:50am- atypical showing of doweling of rebar into rock.
11:20am- last one at the bottom now done. A total of 5 slope anchors are now installed from MH A30 up hill.
12:50pm- More gravel has now been applied to pipe and backfill will now proceed.
1:30pm- Backfill begins with spoil piles.
2:45pm- Excavator working material into place.
3:30pm- Dozer starting its work on the hill.
4:15pm- Dozer working material down the hill as it grades out above the ditch line.
I will now be headed offsite.