Thursday, January 16, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


8:00am- Crew finishing installation of rebar for slope anchors. Concrete to be poured today. 



8:53am- More gravel going in over pipe now. 

9:35am- Concrete going in now. 

9:50am- top one done. 

10:00am- next one down nearing completion. 

10:50am- atypical showing of doweling of rebar into rock. 





11:20am- last one at the bottom now done. A total of 5 slope anchors are now installed from MH A30 up hill. 

12:50pm- More gravel has now been applied to pipe and backfill will now proceed. 

1:30pm- Backfill begins with spoil piles. 

2:45pm- Excavator working material into place. 

3:30pm- Dozer starting its work on the hill. 

4:15pm- Dozer working material down the hill as it grades out above the ditch line. 

I will now be headed offsite. 