Thursday, January 30, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)

7:30am- Rock is now broke out and laying of pipe will resume today. 



8:35am- 1st joint of the day laid in place, as the excavator digs for 2nd joint. 

9:45am- 3rd joint is in. Crew will plug pipe and cover with gravel and then begin backfill for rest of the day.  60’ total laid for today of SDR21, 12”. 

11:20am- Part of the Crew going back and setting lids and wrapping manholes now. 

12:50pm- Another manhole now wrapped. 



1:50pm- manhole getting dug up due to it being backfilled before wrapping was installed. 

2:30pm- another is now wrapped. 

3:20pm- ...and another is dug up for wrapping. 

4:30pm- now fixed. 

5:15pm- last one is now fixed. 