7:50am- Dozer will be working blasted area again today near the substation to get it prepped for digging next week. Drilling crew will be onsite later to drill in bottom area here before rains hit.
9:00am- Blasted area along bluff is now getting leveled out.
10:00am- Gravel stock pile at Access Road 3.
2:45pm- Dozer working now to flatten area between substation and entrance. They are wanting to get it so that a dump truck can haul rock and dump it here along the path of the sewer line.
3:30pm- nothing more will be occurring today other than the dozing. I will now be headed offsite for rest of the day.