Friday, January 24, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:05am- Crew onsite to begin digging and laying pipe again today. 

7:30am- The first joint of pipe going in for the day at STA 262+00. 

8:50am- 4th joint now going in. 

9:50am- Crew digs out for their 7th joint so far today. 



10:55am- 9th joint now laid in place. 

12:00pm- Crew has now laid 10 joints of pipe today for 140’ of 12” sdr35. 
Crew will now begin backfilling and cleaning up area to round out their week. 



1:00pm- Backfill going strong with two excavators lacing finer material over gravel as track loader cleans up behind them. 





2:00pm- Backfill going good with excavators working towards each other. 



Track loader separating bigger rocks from the mix and pushing them out of the way. 

2:40pm- Dig tape is now rolled out over trench on south end. 

Backfill continues along with cleanup. 

3:55pm- crew has almost completely filled ditch line. 





The location of the skidsteer in this picture is where the next manhole will be; MH A35. 