7:05am- Crew onsite to begin digging and laying pipe again today.
7:30am- The first joint of pipe going in for the day at STA 262+00.
8:50am- 4th joint now going in.
9:50am- Crew digs out for their 7th joint so far today.
10:55am- 9th joint now laid in place.
12:00pm- Crew has now laid 10 joints of pipe today for 140’ of 12” sdr35.
Crew will now begin backfilling and cleaning up area to round out their week.


1:00pm- Backfill going strong with two excavators lacing finer material over gravel as track loader cleans up behind them.
1:00pm- Backfill going strong with two excavators lacing finer material over gravel as track loader cleans up behind them.
2:00pm- Backfill going good with excavators working towards each other.
Track loader separating bigger rocks from the mix and pushing them out of the way.
2:40pm- Dig tape is now rolled out over trench on south end.
Backfill continues along with cleanup.
3:55pm- crew has almost completely filled ditch line.
The location of the skidsteer in this picture is where the next manhole will be; MH A35.