7:20am- Crew prepares time lay pipe today.
8:55am- Crew has now laid their first joint of pipe headed upstream from MH A30.
12:10pm- 5 joints of 12” SDR35 are now load in place upstream from MH A30. Areas where slope anchors will be installed are not covered will gravel.
2:45pm- Digging has stopped due to a wall of rock that never shot during blasting. Crew is now working on getting their first slope anchor built.
4:30pm- crew has two slope anchors started, but not tied into rock yet. They are having issues with finding right size drill bit for the holes in the rock. Crew will be picking up site to round out the day.