7:00am- Work will resume on laying 12” Sdr21 with the wintery mix falling this morning.
8:00am- 2nd joint of pipe now laid in place.
8:30am- Jimmy has left the job site sick as Jack takes over laying pipe. 3rd joint now for the day.
9:45am- Pipe laying still going good!
11:20am- 7th joint of pipe now laid as everything is going good.
1:15pm- 10 joints, or 200’ now laid in place. Backfill of this ditch also taking place.
2:20pm- 12th joint now laid. Backfill area is now getting smoothed up with some dozer work.
3:45pm- 14th joint laid.
4:25pm- Digging has stopped. Jack hammer is needed due to ditch becoming to narrow. 280’ of SDR21 is laid today.