Wednesday, January 29, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Work will resume on laying 12” Sdr21 with the wintery mix falling this morning. 

8:00am- 2nd joint of pipe now laid in place. 

8:30am- Jimmy has left the job site sick as Jack takes over laying pipe. 3rd joint now for the day. 

9:45am- Pipe laying still going good!

11:20am- 7th joint of pipe now laid as everything is going good. 

1:15pm- 10 joints, or 200’ now laid in place. Backfill of this ditch also taking place. 



2:20pm- 12th joint now laid. Backfill area is now getting smoothed up with some dozer work. 



3:45pm- 14th joint laid.

4:25pm- Digging has stopped. Jack hammer is needed due to ditch becoming to narrow. 280’ of SDR21 is laid today. 





 


 







No comments:

Post a Comment