Tuesday, January 7, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:40am- Crew has wheel rolled the roadway already this morning on Access Road 2 (Laytons). Gravel is coming so that a defined roadway can be established. 

8:30am- Dozer is working roadway edges back into place as skidsteer spreads out 2” base rock. 



9:40am- Dozer still working to pull material back onto roadway. 

11:30am- Rock continues to be hauled in here on Access Road 2. 

1:00pm- Rock keeps coming. 



1:50pm- Gravel still going down. 

2:35pm- Superior Blasting will be setting off a charge here shortly for today. 

3:25pm-Blast goes off without any issues. 

4:40pm- Base rock is now down to dozer. 

I will now be headed offsite to WWTF. 