Pumping water taking place and the concrete crew is on site to begin tying up rebar.
12:45pm- Excavator was down most of the morning. A hose had come loose internally within the engine compartment and had to be fixed by mechanic.
Rock breaking continues as the rebar mats are getting tied up.
5:30pm- crew has tied up 8 mats today. Rock breaking went ok til end of day as hammer has another leak. Crew will finish working on it in the morning.