Wednesday, September 30, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- crew will continue to do testing today. 

7:52am- test begins on MH A17-18 run. 456’ @ 2 hours & 12 minutes. 

10:09am- test has failed. Crew will need to check for leaks on the test balls again today.  

11:10am- soapy water is sprayed around test balls again today. There is air leaking around the ball in MH A17. Crew will bleed air off line, clean pipe and retest. 

12:27pm- test is now restarted on MH A17-18 run. 

2:41pm- line now passes on MH A17-17 run. I believe the crew now has it figured out! Yes the gauge has gained slightly, maybe due to the sun shining on the lines connecting test equipment...?

3:35pm- crew setting up test for MH A19-20 run. 

3:51pm- now testing MH A19-20 run @ 507’ for 
2 hours and 27 minutes. 

6:16pm- at 2 minutes shy of test I'm calling it as passed. As you can see, once again the gauge has climbed, not decreased...