7:55am- Crew will test some lines today for air leaks.
Starting at A15-16 run where gasket was rolled and repaired.
9:10am- test ball now going in at MH A16.
10:25am- testing issues with the equipment...crew will place test ball into this piece of pipe to see if they can identify the problem.
11:10am- crew cant figure out whats wrong. Rental company will come down to see whats up.
1:10pm- a bad test ball is taken back to Springfield so no testing will occur today.
Crew begins placing rip rap on bank between where the wing dams will go.

2:30pm- another look at the rip rap for stream bank stabilization.
2:30pm- another look at the rip rap for stream bank stabilization.