Tuesday, September 29, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:15am- crew will prepare to test again today starting at MH A15-16 run. 

8:30am- test finally underway now. It will be a 2 hour and roughly 5 minute test. 

10:35am- run from MH A15-16 barely passes air test.  

441’ run. 

12:22pm- testing run A16-17 now. 1hour & 12 minute test. 249’. 

1:34pm- A16-17 run passes. Crew has located a leak on the test plug at the cap. They will be fixing it before using again. This is probably why there is a fall in the gauge during testing...

2:43pm- now testing run from MH A18-19. Rental company is on their way down to fix test ball leak. This shorter run should be fine on time. 
180’ @ 52 minutes. 

3:35pm- A18-19 run passes air test. 

4:22pm- test ball has now been re-soaped to identify the leak for repair. 

4:40pm- repair on ball now being done. 