6:40am- Iowa Trenchless has pulled all equipment and is now offsite. They finished up late last Friday night. They ended up pulling the last joint and turning it to get spacers laying the way they should be.
I was going to check to see if there was any water standing in the pipe, but the pumps apparently were not running over the weekend. I will check when the hole is pumped out again.
8:20qm- Pumping is back underway here at MH A19 location. Crew will work to get it set today.
10:00am- grading out gravel in order to set MH A19.
11:15am- MH A19 is now set and connected to creek crossing.
Crew will now work from MH A20 back to 19 laying pipe once grades are shot and checked.
12:00pm- crew now digging with a new grade of 1.09% from MH A20 - A19.
1:10pm- transit is up and alignment to MH A19 is done.
2:25pm- 1st joint now laid downtown of MH A20.
3:30pm- 3rd now placed.
4:30pm- 4th joint now placed.
5:00pm- backfilling to round out the day.