Wednesday, September 2, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:05am- crew pumping water from MH A14-15 pits so that line can be tied to MH A15 today. 

9:00am- still pumping water at MH A15 side. 

9:55am- invert has to be cut so pipe can be slid back far enough to make connections at MH A15. 

12:05pm- Dirt has been pushed over bank at MH A10 area as crew will level off at static creek level to dig in RipRap wing dams. 

MH A15 now has bench cut down so pipe can go into manhole. 

2:00pm- Bore casing is cut and re-welded so that Casing is straight for creek crossing MH A18-19. 

Also Del-Sha is through at MH A8-9 with pilot hole. 

3:10pm- concrete trench seal will now go in here at MH A16. 

3:30pm- Done. 

3:34pm- trench seal at MH A15 now begins. 

4:05pm- done. 

4:10pm- trench seal at MH A14 begins. 

4:55pm- Done. 