Monday, September 21, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- work on connecting line to A19 manhole will continue today from near STA 71+00. 

7:35am- crew is going to shoot casing in to grade at MH A8-9 creek crossing as casing is just now pulled through. 

8:30am- awaiting welder to cut off pulled head; crew marks out for Bendway weirs adjacent to MH A10 area. 

9:05pm- crew has now shot grade on casing here at A8-9 creek crossing. A8 side they will raise by .14. A9 side os on grade. 

10:40am- crew has spun the casing a 1/2 turn to get a 2.5” low spot out. Grades will now are rechecked. Across casing will be .57%. 

11:30am- trench seals are finished off at MH A18-19 now respectively. 



2:15pm- crew has done some miscellaneous stuff and are now loading the Mule because the front axle is broke. 

2:50pm- flowable fill going in around casing now at last creek crossing. MH A8-9. 

3:40pm- 15yds now around casing. Done. 

5:05pm- MH A19 section is wrapped and strapped today. Crew will again plan to lay pipe onto MH A19 tomorrow, as they were not able to achieve this today. 