Thursday, September 17, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Crew will continue with laying Pipe today and will be at STA 71+00 for encasement later today. 

8:15am- pump is getting changed out due to issues with the other one. 
9:25am- 1st joint going in for today. 

10:10am- 2nd joint placed and getting gravel. 

11:05am- crew has now made it to STA 71+00 and center of dip is marked so that rebar cage can be placed properly. 

11:30am- 3rd joint placed and rebar cage will go in next as pipe is laid. 

1:15pm- bottom half of rebar cage going in now at STA 71+00. 

2:55pm- 5joints total today laid and encasement complete. 









3:15pm- the extra concrete has been put at each side of the creek for a portion of the trench seals here at 18-19.  More concrete will come on Monday to finish these out. 



4:00pm- backfill will now round out rest of the day. 