7:00am- Crew will continue with laying Pipe today and will be at STA 71+00 for encasement later today.
8:15am- pump is getting changed out due to issues with the other one.
9:25am- 1st joint going in for today.
10:10am- 2nd joint placed and getting gravel.
11:05am- crew has now made it to STA 71+00 and center of dip is marked so that rebar cage can be placed properly.
11:30am- 3rd joint placed and rebar cage will go in next as pipe is laid.
1:15pm- bottom half of rebar cage going in now at STA 71+00.
2:55pm- 5joints total today laid and encasement complete.
3:15pm- the extra concrete has been put at each side of the creek for a portion of the trench seals here at 18-19. More concrete will come on Monday to finish these out.
4:00pm- backfill will now round out rest of the day.