Wednesday, September 23, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:10am- crew will get MH A19 tied in today. 

8:30am- gravel now going in for pipe to be laid this morning. One full joint and a partial will get this tie in done. 

9:20am- MH A19 now tied in to each end of the line. Gravel going in now. 

Line lamped by daylight from MH A20-A19. 

10:35am- A lip on MH A19 has now been repaired. 

11:10am- another section going on MH A19; gettting wrapped and then strapped. 

12:45pm- top section now on MH A19 with wrapping and strapping to come. MH A18 side getting marked out for Rip Rap. 
12:55pm- MH A19 is almost completed. 

2:50pm- cleanup on MH A19 side is going on now. 

4:10pm- grading around A19-20 continues. 