7:00am- Del-Sha is not onsite yet. They are currently reaming back with the 18” bit.
7:20am- crew will continue their work to open cut here at MH A18-19.
8:50am- crew prepares to install a culvert to help bypass the water so that rest of the rock can be broke out.
-Progress meetings @ TCRSD Office.
12:05pm- rock is removed from trench back to where more breaking will occur. Black pipe supporting 6”pump hose as water is being pumped across ditch.
1:45pm- all rock is now removed from top of bore hole. Crew will work to get casing laid today.
2:55pm- gravel is getting graded out for casing.
4:30pm- casing is now in place.
4:50pm- crew cleaning off rock now for concrete in the late morning.