7:00am- Crew to concrete creek crossing today and get carrier pipe placed in casing.
Top soil also getting spread in area of MH A17-18.
8:55am- crew has epoxied rebar in and crossed and tied them together ip and down the casing. Now awaiting concrete.
9:55am- concrete going in.
10:30am- still going with 4th load.
11:30am- load six for 54yds so far.
11:55am- 72 yds now.
1:05pm- encasement over creek area now completed. 90 yds of concrete was poured here today. Both ends will be tied in later on when trench seals are done.
2:25pm- crew loading bore now with carrier pipe here at MH A18-19 crossing.
A look through casing as pipe is being loaded.
3:45pm- about half way through casing now. Crew jad to stop and place spacers on more pipe.
4:45pm- carrier pipe now in place.
Looking from MH A18 through casing and carrier towards MH A19 location. Crew will joint short section at 18 tomorrow and get MH A19 set.
5:00pm- creek is opened back up so it can flow again.