Monday, September 28, 2020

Turkey Creek Ph 1 - RL Persons (L.S.)


6:45am- crew is back today to begin cutting asphalt for final repairs and to do a “punch list” of sorts on some remaining items. (i.e.; bollards, safety grate install)

3:00pm- crew has asphalt ready for concrete of which they will do tomorrow. 



Safety Grate will go on tomorrow. 

Nuts are tightened on catwalk. 

Valve indicators are getting installed. 