6:45am- crew is back today to begin cutting asphalt for final repairs and to do a “punch list” of sorts on some remaining items. (i.e.; bollards, safety grate install)
3:00pm- crew has asphalt ready for concrete of which they will do tomorrow.
Safety Grate will go on tomorrow.
Nuts are tightened on catwalk.
Valve indicators are getting installed.