Friday, September 4, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:45am- receiving pit at Bore 1 will get flowable fill this morning so that Rail Pros can get offsite. 

8:05am- Flowable fill has finally arrived onsite. 

8:35am-receiving pit now filled to RailRoad R.O.W.

9:05am- RailPros representative said to cover with dirt and call it good. 18 yds of flowable fill material was used. 

10:10am- rip rap going in on MH A15 side. 

Also stream bank work continues today near MH A10. 

11:00am- creek at MH A18-18 crossing will begin getting dam put across it so that the open cut can begin next week. 

11:40an- Water is down to a slow trickle at the leaking joint 98’ upstream of MH A15. Crew is in the pipe pushing the gasket back under it. 

1:00pm- creek is now diverted and rock breaking is underway at MH A18-19. 




-1:25pm- crew will continue to work on leak in pipe, break rock and do some general cleanup moving dirt around. I will be headed offsite and will be back next Tuesday after the Holiday. 