7:00am- crew will pick back up at tying in MH A15 to bore.
8:25am- two joints of pipe are now placed as crew will have to slice in two more shorter pieces to get to manhole.
9:55am- pipe now ties MH A15 to bore.
10:20am- boot now installed at casing and carrier pipe.
11:10am- Building back of Stream bank is now taking shape near MH A10 location.
11:55am- MH A15 area backfilled, manhole wrapped and strapped except for straps on top section of which will follow.
1:40pm- rip rap bank stabilization is now done at creek crossing MH A16-17.
Also at this time excavator digging at MH A18 to reset last Joint of pipe laid before setting manhole here.
2:40pm- after much debate, the crew has decided not to pull the pipe due to the fear of it not coming apart at first joint and pulling apart somewhere else... so with this creek crossing now going to be an open cut with casing; they can make up the difference from MH A19-20 run.
3:10pm- a joint of pipe is now laid.
4:00pm- MH A18 base going in.
5:05pm- base now set and connection to downstream pipe is completed.
5:30pm- pipe is flowing water between MH A16&15.
They believe its a rolled gasket upstream of MH A15 about 98’ or so... they will be trying to fix it from the inside possibly tomorrow.