Thursday, October 1, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


8:00am- crew setting up to test MH A20-21 now. 

8:35am- MH A20-21 run is now under test. 387’ @ 1 hour and 52 minutes. 

10:32am- test has failed. Crew will soap the test balls and check for leaks at each end. 

10:59am- no leaks were detected at each ball, so crew has chosen to air back up and retest. 
Back on test now from MH A20-21 run. 387’ @ 1 hour and 52 minutes. 

12:52pm- line now passes air test from MH A20-21. 

1:42pm- now testing run from MH A21-22. 298’@ 1 hour and 16 minutes. 

2:58pm- line passes air test from MH A21-22. 

3:42 pm- crew has moved the test equipment to the next set up for testing on MH A22-23. 
Due to time they will not start this test until Monday. 
I will be headed offsite. 