Monday, October 12, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- Trench seal on MH A9 side poured last Friday. 

Wing dams were also worked on last Friday. 





9:02am- air test now underway at MH A26-E1. 220’ @  1 hour and 4 minutes. 



10:06am- air test passes. 

10:15am- wrapping and strapping MH A8. 

12:00pm- manhole completed and trench seal now in place. 



1:10pm- MH A18 top is now being wrapped and strapped. 

2:00pm- crew will be cleaning up areas and will begin moving equipment to final area to lay pipe from MH A3 to A6. Access 3 roadway has now been graded out for most of the way with 2” base rock. 

I’ll be headed off til tomorrow. 