Wednesday, October 14, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Crew will start laying pipe today at MH A3 location. 

7:45am- crew shooting grade on bore casing so that MH A3 can be set accordingly. 

8:50am- rock is now broke out and debris removed for the setting of MH A3. 

11:05am- grading out for manhole A3. 

11:55am- MH A3 base now set and connected to RR01 bore at WWTF. 

- 12:15 to 3:00pm: Met with Engineer, TCRSD, and Big Cedar at new Liftstaion site to go over everything. 

3:10pm- 1st joint now laid upstream of MH A3 with wrapping and strapping of manhole occurring. 

4:35pm- backfill begins to round out the day here. 