6:45am- crew to continue with laying of pipe today as well as beginning to set gate posts per plans.
8:10am- 1st joint of the day getting gravel.
9:40am- 2nd joint is in. Rock is not broke real well so excavator is trying to rip it out.
11:00am- 5th joint now being placed.
11:30am- 6th now getting placed.
1:10pm- #8 now going in.
2:30pm- Joint 10 ready for gravel.
3:30pm- #11 getting gravel.
4:40pm- 12th and final joint for today as more unblasted rock is encountered.