Tuesday, October 20, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:50am- hole is pumped down this morning so digging will resume here shortly upstream of MH A3. 

8:30am- 2nd joint now being placed. 

Pump discharge hose still leaking from last week. 

9:30am- 4th joint going in as rain begins to fall today. 

10:35am- 5th joint now in so far and pump is moved up again. 

12:00pm- 7th joint now laid. 

12:10pm- crew is calling it a day. Rains continuing with no end in site...