Monday, October 5, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:15am- a crew will be laying line from MH A9 towards creek bore today, and another crew will be testing line from MH A22-23. 
Creek crossing between MH A8-9. 

MH A22-23 testing to begin here shortly. 

9:10am- grades are getting shot ar MH A9 so pipe laying can start. 

9:20am- testing of line from MH A22-23 is now underway. 778’ @ 3 hours and 45 minutes. 

11:15am- crew now has pipe leaving MH A9 headed to bore and MH A8. 

11:55am- test on line has already failed. Crew has checked for leaks and found none. They will air up line again and then restart the time. 

12:04pm- test is now back underway from MH A22-23. 778’ @ 3 hours and 45 minutes. 

1:30pm- another joint now laid. 

1:18pm- I notified the crew about air loss on the test. 

2:00pm- crew decides to re-air again, but this time at a slower rate...

2:05pm- back under testing again for the 3rd time. MH A22-23. 
2:30pm- MH A9 has another section wrapped and strapped. 

3:55pm- pipe crew has stopped laying pipe and are now installing spacers on pipe so pipe can be placed into casing. Approximately 2.5 joints of pipe laid today. 

5:44pm- Line from MH A22-23 passes air test. As you can see again, the line has increased in pressure. I have asked that a different test box be used tomorrow to see what the difference will be, if any.

Large boulders were also hauled to the site today for bend way weirs. 