7:15am- a crew will be laying line from MH A9 towards creek bore today, and another crew will be testing line from MH A22-23.
Creek crossing between MH A8-9.

MH A22-23 testing to begin here shortly.
9:10am- grades are getting shot ar MH A9 so pipe laying can start.
9:20am- testing of line from MH A22-23 is now underway. 778’ @ 3 hours and 45 minutes.
11:15am- crew now has pipe leaving MH A9 headed to bore and MH A8.
11:55am- test on line has already failed. Crew has checked for leaks and found none. They will air up line again and then restart the time.
12:04pm- test is now back underway from MH A22-23. 778’ @ 3 hours and 45 minutes.
1:30pm- another joint now laid.
1:18pm- I notified the crew about air loss on the test.
2:00pm- crew decides to re-air again, but this time at a slower rate...
2:05pm- back under testing again for the 3rd time. MH A22-23.

3:55pm- pipe crew has stopped laying pipe and are now installing spacers on pipe so pipe can be placed into casing. Approximately 2.5 joints of pipe laid today.
5:44pm- Line from MH A22-23 passes air test. As you can see again, the line has increased in pressure. I have asked that a different test box be used tomorrow to see what the difference will be, if any.
Large boulders were also hauled to the site today for bend way weirs.
MH A22-23 testing to begin here shortly.
9:10am- grades are getting shot ar MH A9 so pipe laying can start.
9:20am- testing of line from MH A22-23 is now underway. 778’ @ 3 hours and 45 minutes.
11:15am- crew now has pipe leaving MH A9 headed to bore and MH A8.
11:55am- test on line has already failed. Crew has checked for leaks and found none. They will air up line again and then restart the time.
12:04pm- test is now back underway from MH A22-23. 778’ @ 3 hours and 45 minutes.
1:30pm- another joint now laid.
1:18pm- I notified the crew about air loss on the test.
2:00pm- crew decides to re-air again, but this time at a slower rate...
2:05pm- back under testing again for the 3rd time. MH A22-23.
2:30pm- MH A9 has another section wrapped and strapped.
3:55pm- pipe crew has stopped laying pipe and are now installing spacers on pipe so pipe can be placed into casing. Approximately 2.5 joints of pipe laid today.
5:44pm- Line from MH A22-23 passes air test. As you can see again, the line has increased in pressure. I have asked that a different test box be used tomorrow to see what the difference will be, if any.
Large boulders were also hauled to the site today for bend way weirs.