Wednesday, October 7, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


7:00am- more testing today. Next run to be tested is between MH A24-25. Pipe work will also continue at MH A9-A8, and the water line at Mr.Heads will get encased today. 

7:37am- test is now underway from MH A24-25 line run. 272’@ 1 hour and 19 minutes. 

8:20am- digging starting at Water line encasement on Head property. 

9:40am- over on test time, but line passes without any issues with the different test box used again today. 

9:55am- 2 more joints of pipe are laid downstream of MH A9.. Backfilling now so the excavator can get out over pipe to dig for tie in at casing. 

10:50am- ditch is now dug across Heads road and casing placed with new CTS water line. 

Base rock getting placed per owners request. 

Crew will cleanup area here and then go back to start another line test yet today on the 27” pipe. 

12:15pm- pipe crew has been breaking rock for tie in. 

2:50pm- pipe will now come together with carrier pipe in casing. 

3:10pm- connection made! Tracer wire is now getting tied together. 

3:20pm- gravel now getting placed. 

3:45pm- boot going on.

3:50pm- graveling rest of the way up now and backfill will round out the day. 


-No other line testing was done today due to the water line encasement on Heads property. 