Tuesday, October 6, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


6:55am- More work on Access 3 today getting it cleaned up. Testing will also continue. 

7:45am- crew getting test balls placed and inflated for the next run of line to be tested. MH A23-24 run. 

8:30am- test is now started on MH A23-24 line run. The other test box wont be onsite until mid day. 
This run will test for 3 hours and 23 minutes @ 701’. 

9:50am- pipe crew digging out to get pipe installed in bore casing today at MH A8-9 creek crossing. 

11:59am- a few minutes over required time, but its right at passing the air test. MH A23-24. 

2:01pm- another test is now setup on the line from MH A25-26. A different test box is attached. 904’ @4 hours and 22 minutes. 



2:50pm- carrier pipe is now loaded into casing ar creek crossing A8-A9. 

4:20pm- digging proceeds on line from MH A9 on towards carrier pipe thats now in the casing. 

5:05pm- 1 joint of pipe laid today in the ditch. Backfilling now to round out their day. 

6:18pm- testing is now being called as “passed”from MH A25-26, with 4 minutes remaining. The gauge has has risen, but only from 3.9 to 4.1 with this test different test box. 