Tuesday, October 13, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


More line testing today along with equipment being moved to last section of line to be laid from MH A3 - A6. 
7:45am- crew moving pump out of area A3 to exchange it for a different one due to it  not running. 

9:30am- testing line from A26-27 now. 12” line at 364’ for 21 minutes. 




9:50am- Line from A26-26 passes air test. 

10:13am- line from A27-28 now under test. 109’ for 11 minutes. 

10:23am- line A27-28 passes test. 

10:50am- MH A27 passes vacuum test. 

11:25am- MH A26 passes vacuum test. 

2:15pm- MH E1 has now passed air test. Crew had to install an additional test ball on stub out side due to cap leaking air. 

3:10pm- MH A25 passes vacuum test. 

4:36pm- MH A24 passes vacuum test. 

No more testing today. Testing will resume at MH A23 possibly tomorrow. 