Thursday, October 8, 2020

Turkey Creek Ph 1- Flat Creek (Line Work)


Crews will he digging to set MH A8 and get last tie in done on this side. 
More line testing will also occur today. 
7:50am- crew begins with having to haul off spoils so that they have room to get MH A8 placed today. 

9:30am- still moving material before setting MH A8 today. Also, no testing of lines will now occur today. Not enough people to make it happen. 

10:25am- rock is now being broke out at MH A8 location. 

11:30am- still digging to het MH A8 set. 

1:40pm- back to breaking rock. 

2:45pm- gravel finally going down for MH A8 base placement. 

3:40pm- MH A8 base is now set in place. 

5:20pm- last pipe connection almost completed. 

7:55pm- gravel going in now. 

6:00pm- boot now on casing and pipe. Crew will gavel up and head home. 







 