Thursday, October 15, 2020

Turkey Creek Ph 1 - Flat Creek (Line Work)


Crew will be trading out excavator for a different one here at MH A3 location first thing this morning. It will he a slow start today. 
8:30am- Excavator swap day is now done. Crew will begin laying pipe here shortly. 

9:10am- two pumps running to pump the water away from hole. 
10:25am- water is down now as crew will break rock first thing. 

11:20am- no progress really; Excavator is currently being worked on...

-12:15-3:15pm: meeting at Branson Creek with Engineer, TCRSD and Tom Boyce. 

3:20pm- 1st joint of pipe getting gravel so far today. 

4:30pm- 2nd joint laid. Crew will now move pumps. 

4:50pm- a bad discharge hose will now need replaced. Crew is done foe the week. 








No comments:

Post a Comment