Crew will be trading out excavator for a different one here at MH A3 location first thing this morning. It will he a slow start today.
8:30am- Excavator swap day is now done. Crew will begin laying pipe here shortly.
9:10am- two pumps running to pump the water away from hole.
10:25am- water is down now as crew will break rock first thing.
11:20am- no progress really; Excavator is currently being worked on...
-12:15-3:15pm: meeting at Branson Creek with Engineer, TCRSD and Tom Boyce.
3:20pm- 1st joint of pipe getting gravel so far today.
4:30pm- 2nd joint laid. Crew will now move pumps.
4:50pm- a bad discharge hose will now need replaced. Crew is done foe the week.